Spencer, IA (KICD)–The Spencer City Council approved a pair of project bids that came in¬†approximately $30,000 under budget on Monday evening.
City Engineer Jim Thiesse says they received five bids for the Parking Lot Improvement Project.

Vaughn Deloss Construction’s bid of $223,786.50 for the 2014 Fairway Woods First Addition PCC Paving Project came in well under the $245,000 estimate.

Thiesse talked about why he feels the bids came in under estimates.

Looking ahead bids for the 2014 East 18th Street Overlay Project are slated to come in on February 18th.¬† The estimated cost is $236,000 with $120,000 in federal funding and the remainder to be be paid out of the city’s Street Reserve Fund.

Local Headlines

in Local

Spencer High School Principal Reflects on Graduating Class

Graduation

Principal Elli Wiemers tells KICD News about the legacy of Spencer High School Class of 2015...

in Local

Bicyclist Struck

ambulance2

A Sioux Center man is injured after being struck by a vehicle while riding a bike.

in Local

Avian Influenza Friday

Bird Flu 1240

Another probable case of Avian Influenza is found in northwest Iowa.

in Local

Iowa Egg Production

eggsag

Iowa egg production for April fell 8 percent from the month before and 4 percent from a year ago as the bird flu claimed millions of egg-laying hens.

in Local

Budget Debate

statehouse

Iowa lawmakers say they've made progress in determining how much to spend on the state's overall budget, including K-12 education.